Silverdale Trails – Underground Detention System

Concrete pouring recently commenced for the new underground stormwater detention vault at the Silverdale Trails retail development in Silverdale, Washington.

Utilizing two 61-meter concrete pumps, Apeland Concrete pumped approximately 1,000-yards of CalPortland concrete in under 10 hours to complete the vault’s entire slab and footing pour.  A task that would require roughly 100 ready-mix concrete trucks.

Larger than a football field, this underground detention system is being installed under the shopping center’s future parking lot on the eastern-central portion of the site.  It is designed to contain all of the stormwater runoff on the parking lot, and through the 1,000 gallon per minute filtration system, dissipate water into the earth opposed to being forced offsite in a storm event.

The Silverdale Trails is a 212,000 square foot shopping center situated on an approximate 18 acre site at Kitsap Mall Boulevard and Greaves Way.  The site sits against a natural backdrop of old growth timber and natural wetlands with views of Mt. Rainier and Puget Sound.

Share this news:

See More News

The images show the 70th anniversary of Robinson Construction Co.

Robinson Construction Co. Celebrates 70 Years in DJC Oregon’s Milestones 2024

We are thrilled to share that Robinson Construction Co. has been featured in DJC Oregon’s…

Read More
Portland Rock Gym is featured in the Daily Journal of Commerce Oregon.

From Retail to Rock Gym: Portland Rock Gym’s Feature in DJC Oregon

The vibrant city of Portland is known for its innovative and dynamic approach to urban…

Read More
Grand Ridge Plaza BevMo!

Grand Ridge Plaza Earns LEED Certification

Robinson Construction Co. was selected by Regency Centers Corporation to construct a six-structure, 43,100-square foot…

Read More

Ready to kickstart your project?

At your service to transform your construction vision into a concrete reality. Get in touch with our team today to delve into your project requirements.
Contact Us